Filter content by area of interest
Ports & Terminals
Port AuthoritiesContainerBulkBreakbulk/General CargoRo-Ro/AutomotiveGTOs
Cargo Handling Equipment
STS CranesYard CranesMobile CHERo-Ro EquipmentBreakbulk EquipmentLow ThroughputBulk Handling Equipment
Shipping & Logistics
Container ShippingBreakbulk/General CargoRo-Ro ShippingDry Bulk ShippingLiquid cargoesLogistics
ICT
TOSPlanning & Optimisation TechnologyWiFiMobile ComputingPort Community SystemsAsset Tracking & Monitoring
Automation
Automated EquipmentGate AutomationRemote ControlProcess Automation
Multimodal
RailInland WaterwaysShortsea ShippingRoadAir-Cargo
Container Industry
Container manufactureContainer leasingRepair/StorageTradingConversion/Innovation
Refrigeration
Operations/TransportContainer leasingEquipmentM&R/Storage
Breakbulk
General cargoProject Cargo/Heavy LiftForest productsRo-Ro/AutomotiveAgribulks
Safety & Security
InsuranceHazardous cargoLashings/SecuringLegal/Regulatory
Civil Engineering
Port & terminal construction/designCivil & Consulting EngineersDredging & ReclamationMooring & FenderingLightingPaving & Surfacing
Environment
Business
InsuranceLegal/RegulatoryAppointments/PeopleMergers/Acquisitions/RestructuringFinance/Financial ResultsTrade & Professional AssociationsBusiness/Commerce Miscellaneous
 View all Topics View all Topics A-Z
More View all Topics View all Topics A-Z

You are viewing 1 of your 1 guest articles


register  or  login  for full access to online news

Milestones for Panama Canal expansion

June has been an important month for the Panama Canal expansion project, with several milestones reached.
Linked InTwitterFacebook

The project has moved forward with the filling of the locks on the Atlantic side and the rolling gate’s first operational tests.

The filling of the locks began in early June in the lower chamber on the Atlantic side. To fill the locks, five pipes with 0.9m diameter allowed 50,000 cu metres water to flow in from Gatan Lake, at 9 inches/hour. A similar process was performed last week on the Pacific side.

The test on one of the heaviest rolling gates was carried out successfully on the Atlantic side. The first operational test, which integrated mechanical and electrical systems, as well as positioning speed sensors, allowed verification of position data, weight and buoyancy. 

An identical process will take place on each of the other eight gates from the new locks on the Atlantic side.

“My team and I are very proud of the significant progress we have reached in the last month. As we approach the finalisation of expansion programme, we will have materialised one of the most important engineering pieces in the world – not only because of its complexity, by also because of the benefits it will provide to the global maritime community,” said executive vice president of engineering and programme management, Ilya de Marotta.
Linked InTwitterFacebookeCard

You may also be interested in...

UK logistics sees the cup only half full

Nanaimo gets funding

New Tukan 2000 for Kaliningrad exclave

More for Chancay

SA-TU Vuosaari step up

ICTSI named for Kribi port

Related Stories

P&O Ferries to launch Calais-Tilbury unaccompanied ro-ro service

P&O Ferries is launching a Calais-Tilbury ro-ro service for unaccompanied traile...

DNV GL's route to a low carbon future

DNV GL - Maritime has released the third edition of its Maritime Forecast to 205...

CMA CGM launches Rhine Valley Rail

The new intermodal rail service connects the Port of Rotterdam with the German h...

New caller for DaChan Bay Terminals

Hyundai Merchant Marine’s Korea Middle-East Express (KME) service, has begun cal...
Linked In
Twitter